Reviews Entered for Project: City Yard Improvements (ID 11737 Phase: Initial Request)
By Reviewer ecreal on February 8, 2019 at 4:08 PM
Scores
(Only one Project Type should have scores.)
Project Type: Programmatic
Future Needs Impact Priorities Collaboration
Project Type: Internal City Operations
Sustainability Impact Health/Safety Costs
3: Adequate, with room for improvement 4: Good 3: Adequate, with room for improvement 3: Adequate, with room for improvement
Project Type: Infrastructure
Impact Priorities Existing System Economic Development Collaboration
Project Type: External Operations
Sustainability Impact Health/Safety Costs
Reviewer Comments

Other than upgrading fencing to meet new code requirements there is no justifications made for these requests. Include a breakdown of how the funds would be expended. More explicit explanation of upgrades especially for the Tool room could have justified higher score. Is this enough funding to perform all of the improvements listed?